[caption id="attachment_694" align="alignleft" width="225"] Fuels! A mix of gasoline and diesel, that the CE team synthesized from carbon captured out of the air and hydrogen split from water, all powered with clean electricity.[/caption] Last week, the Carbon Engineering team demonstrated “Air to Fuels” by directly synthesizing...

It has been roughly a year since we broke ground in Squamish, and we now have our full end-to-end air capture demonstration plant up and running. The entire CE team, with the support of our collaborators and suppliers, has been hard at work to make...

Construction and commissioning of CE’s pilot plant is continuing in Squamish, BC. A lot has happened in the last few months, and we now have most of the major equipment at site and installed. A big effort for us in recent weeks has been to...

Construction is deep under way at our Squamish demo plant site. The CE team has been working toward getting the air scrubber and pellet reactor installed these past two months. We call this the “wet end” of the plant, since both components circulate liquid, to...

The installation of our demonstration plant in Squamish is now well underway. Site preparation and concrete pouring for equipment foundations started in January and are now complete. In the past several weeks, major pieces pre-fabricated equipment – including the Air Contactor and Pellet Reactor –...

The CE team is excited to have broken ground on our new pilot demonstration project this week in Squamish, BC. For the past year, we've been working diligently on financing and engineering our most ambitious hardware demonstration project yet. We are now entering the construction...

We are thrilled at the recent publication of a Harvard Business School case study centered on Carbon Engineering. We have been working with HBS Professor Joseph Lassiter and case writer Sid Misra for the past few months as they pulled this case together, and it...